City money

Chicago plans $18.1 billion in building and repairs over five years. Each ward also gets $1.5 million a year for street projects its alderperson picks.

Five-year plan 2025–2029 · ward street money through Sept. 30, 2026 · checked Nov. 11, 2026

$18.1Bin the city’s five-year building plan, 2025–2029
$6.0Bof it for O’Hare and Midway airports
$67.9Mof $75M in ward street money committed by Sept. 30, 2026
2,105ward street projects listed: repaving, sidewalks, speed humps, lights

The city’s five-year building plan, 2025–2029

$18.1 billion by program. About 40% is borrowing repaid from airport, water and sewer revenue; the rest comes from city bonds, TIF, federal, state and other money.

O’Hare and Midway airports
$6.0B
Water system
$3.7B
Streets, bridges and transit
$3.0B
Sewers
$1.9B
Neighborhood streets, alleys and lights
$1.4B
Economic development
$816M
City vehicles
$460M
City buildings
$388M
Information technology and other
$176M
Lakefront and shoreline
$150M
Public spaces (City Space)
$86M

The plan is updated each year; this is the most recent one the city has published. Information technology isn’t printed as its own total; it’s the rest of the $18.1 billion.

Ward street money: what alderpeople picked

$67.9 million committed of $75 million for 2026, through Sept. 30. Every ward gets $1.5 million a year.

Repaving streets and alleys
$49.0M
Sidewalks
$9.3M
Traffic safety
$4.2M
Street lights
$2.7M
Schools and parks
$1.7M
Other
$1.0M

Ward by ward

Share of each ward’s 2026 street money committed by Sept. 30.

Tap or point at a ward to see its numbers.

All of it90–99%70–89%Under 70%

Most money not yet committed (incl. past years)

Ward 33
$705K
Ward 42
$699K
Ward 15
$678K
Ward 22
$657K
Ward 34
$614K
Ward 30
$561K

Most on sidewalks

Ward 13
$1.03M
Ward 46
$931K
Ward 3
$743K
Ward 25
$511K
Ward 10
$479K
Ward 28
$395K

9 of 50 wards had committed all $1.5 million by Sept. 30. Each ward’s page lists what its money went to.

No official target

The plan is the city’s own list of intended projects

There is no outside target for capital spending. The five-year plan says what the city intends to build and how it expects to pay; the ward money has to be committed by each alderperson, and what isn’t committed carries over. The 2025–2029 plan (PDF) ›

Program totals are the five-year plan’s own charts. Ward street money is the city’s third-quarter report: we read each project’s type and estimated cost and grouped the types. Our totals match each ward’s committed total except Ward 16, where the listed projects add up to $7,730 more. The plan lists what the city intends to spend, not what it spent.

Sources: City of Chicago, 2025–2029 Capital Improvement Program · City of Chicago, 2026 Q3 Aldermanic Menu Report